The City Council considered a contract amendment with PlaceWorks for San Pablo creek restoration analysis. During the initial review phase, PlaceWorks identified the need for additional work tasks including a detailed topographic survey and a hydrologic model. The additional work would provide essential background data for any future San Pablo creek restoration plans.

  • Staff Recommendation - Staff recommended the City Council approve the contract amendment to increase the cost by $59,960.

  • Action - The City Council approved the contract amendment as recommended by staff.